Energy Minister Dr John Abdulai Jinapor expects Kumasi line works, which he links to current power challenges, to finish by 10 or 11 December 2026.

Speaking on Asempa FM, Jinapor said crews were replacing old transmission lines in parts of the densely populated city. They must switch off some sections of the network to carry out the work.

“In Kumasi, which is densely populated, we are changing the old lines with new ones, so we turn off a section in order to work on the other section and vice versa. But by December 10, 2026, they would be done,” he said.

The minister acknowledged that residents could face disruptions and pressure on supply during the exercise. He asked them to bear with the authorities and warned that postponing the work could expose the system to shutdowns later.

His timeline runs beyond an earlier target for a major upgrade in the city. In a joint statement on 29 October, the Ghana Grid Company (GRIDCo) and the Electricity Company of Ghana (ECG) said the 161kV Anwomaso-Ahodwo line upgrade was 70 per cent complete. They announced planned outages from 30 October to 29 November and expected to finish by the end of that month.

Work on that line began on 20 July as a three-month project. NewsGhana reported this month that the Kumasi upgrade had run past its original schedule.

More planned cuts are already under way in the Ashanti Region. A notice ECG issued on 21 November set daily outages in parts of the region from 26 November to 1 December, between 7:30am and 5pm.

Those interruptions are for GRIDCo’s work on the transmission line from Anwomaso to the Ridge Bulk Supply Point. ECG said GRIDCo was replacing a single-circuit line rated at 364 megavolt-amperes (MVA) with a double-circuit system. Each of the two new circuits is rated at 488MVA.

A separate fault also hit supply this week. GRIDCo said on 25 November that illegal chainsaw operators had felled a large tree onto the 330kV Aboadze-Anwomaso transmission line, causing it to trip. System operators reduced supply to parts of Kumasi because the line was unavailable.

Jinapor said ECG was also carrying out extensive maintenance in Accra, which could cause occasional disruptions. He assured the public they would be informed when such situations arose.

“There is no cause for alarm,” he said.